The owner-operator of a 5 TPD paddy-straw CBG plant in Punjab on collection, storage, pre-processing and the digester, three months after commissioning.
Grass2Gas Biofuels’ plant in Moga, Punjab, started producing compressed biogas in August 2026. It is a 5 TPD plant, designed to run on about 15,000 tonnes of paddy straw a year, co-digested with cow dung. Three months in, I can say two things with confidence. Paddy straw is the most difficult CBG feedstock in India. But the straw itself is rarely what breaks a plant. What breaks it is underestimating everything that happens before the straw reaches the digester.
These are the lessons from our first months, from the field to the digester.
Why straw is different
Paddy straw is dry, light and bulky. It is rich in lignin and silica, which make it slow to break down and hard on machinery. And it is available for only a few weeks a year. Everything a straw plant needs for twelve months has to be collected in one short window, stored for up to a year, and then fed to the digester every single day.
Each of those steps can stop a plant. Most of the work is in making sure none of them does.
The collection window
We get roughly a month between the paddy harvest and wheat sowing. In that month the year’s feedstock has to be baled, lifted and moved. The decisions made in those few weeks set the plant’s feed for the next eleven months.
We do not bale ourselves. We work with vendors who run different balers at very different capacities, so there is no single “collection rate” to plan around. What we can control is what our plant can accept. We designed our pre-processing to handle bales of different sizes, shapes and densities, so we are not tied to one type of baler. A plant that can handle only one bale type has narrowed its window before the season even starts.
This season we collected about 10,000 tonnes from around 20 villages. Since commissioning, the plant has run on about 5,000 tonnes bought from the 2025 harvest.
The market shapes the season too. Straw prices were high at the end of last year, so this year vendors hurried to bale early. Plan for the market, not just the weather.
Storage: a year of fuel in the open
Our bales are stored in the open at three sites near the plant. That is a full year of fuel sitting outdoors.
Degradation has not been a serious problem for us. Fire has been the real risk. Last year we had small fires on two or three occasions. None was large, but each one was a warning. This year we have planned the stacking better. We are still learning, and I expect storage to teach us more than any other part of the operation over the next few seasons.
“Treat the straw yard as part of the plant, not as a warehouse.”
Old straw is not dead straw
Before commissioning, I was sure biogas output would drop sharply on straw that had sat through a season. It has not happened. We have run on last season’s paddy straw since August and the results have been good.
We are collecting fresh straw this year. But the fear about old straw was bigger than the reality, at least on our plant.
Pre-processing is where straw is won or lost
Straw reaches the plant as bales of different shapes, sizes and densities. The digester needs a uniform feed every day. Everything between those two points is pre-processing.
We designed our own pre-processing line. It shreds the straw, mixes it and extrudes it before it reaches the digester. Getting it right took a great deal of effort, meticulous design and precision engineering. It now runs successfully, and it is the part of the plant I am proudest of.
We run no separate pre-treatment stage. There is no soaking and no holding step. Bales go from the yard to the debaler, then on a continuous line to the feed tank. That continuous flow is a large part of why the plant runs efficiently.
“Fewer steps mean fewer places for the process to stall.”
Silica and lignin are the two problems everyone warns you about with straw. We have not had to fight them day to day. That is not luck. It comes from the pre-processing line and the plant design, both settled before the first bale arrived.
The digester: better than the book
We co-digest straw with cow dung. Our gas yield per tonne of feedstock has been better than the textbook figures we planned with. That has been the most welcome surprise of our first months.
The plant is running at about half its capacity and scaling up. Alongside the biogas, it is designed to produce around 40 tonnes a day of fermented organic manure, which is the other half of a straw plant’s output.
A designer–builder partnership
The plant was designed by Dr. Srinivas Kasulla, during his time at a previous company and before he founded Tattva. The design was his. Execution, commissioning and day-to-day operation are ours at Grass2Gas. He was thoroughly professional throughout, and the decision I value most came from him. Our original plan used PSA for biogas upgrading. Srinivas assessed the market and recommended membrane technology instead. It stretched our budget, and our team worked hard to deliver it. It has been one of the best decisions we made.
Lessons for anyone planning a paddy straw CBG plant
- Be confident. Straw is harder than other feedstocks, but it can be run well.
- Visit as many straw-based plants as you can before you finalise anything. Watch them run.
- Design right from the start. Pre-processing and the feed line decide most of what follows.
- Plan storage and fire safety as seriously as the digester.
- Choose advisers and partners with skin in the game, people whose advice has been tested on a running plant.
“Paddy straw is unforgiving of shortcuts. It rewards design done right.”
Paddy straw is often discussed as a waste management problem. For those of us running plants on it, it is a supply chain, logistics, engineering and process problem, all at once.
Three months cannot prove everything about a feedstock that has to work season after season, and we are still learning every week. But our experience so far tells me paddy straw deserves more confidence than it gets.
The question is not whether paddy straw can produce CBG. It is whether we are willing to design the whole system around the realities of handling it.